Grants:PEG/WM ID/Wikimedia Cipta/Report

Bismillah
Report accepted
This report for a Project and Event grant approved in FY 2010-11 has been reviewed and accepted by the Wikimedia Foundation.
  • You may still comment on this report on its discussion page, or visit the discussion page to read the discussion about this report.
  • You are welcome to Email grants at wikimedia dot org at any time if you have questions or concerns about this report.



Wikimedia Creates

Wikimedia Cipta initiated with the goal to enable Wikimedia Indonesia as a coordinating institution to foster ideas and future innovation from Indonesian volunteers using wikimedia projects.

Activity edit

Project Goal edit

  • The key success measure for this project to create and support new projects and its Project Directors and their team for Wikimedia Foundation chapter grant in June 2011 not accomplished due to administrative issue re: agreement and grant between Wikimedia Indonesia and Wikimedia Foundation.
  • The class project under Wikimedia Cipta Jakarta redesigned in addressing this issue to make sure activities still rolling to pursue other goals in reversing the editor trend, has been accomplished.

Summary of Best Practice and Lesson Learn under Wikimedia Cipta Project edit

What impact did the project have on WMF mission goals of Increased Reach, Increased Quality, Increased Credibility, Increased and Diversified Participation?

  • The project is successfully increased reach in two cities: Semarang and Bandung for two intervention project in Javanese and Sundanese language Wikipedia. While noting potential reach in Samarinda or Banjarmasin, Kalimantan. In Jakarta, the project increased volunteer capacity and diversified participation by open call and cooperation with Lontar Digital Library (librarian, professional translators, and writers).
Readership rate
Project result in statistic of active wikipedians.
  • In general Indonesian language Wikipedia performance remain impressive. In October 2011 statistic, while Indonesian Language very active contributor numbers are in the same growth rate as (high comparison) Bulgarian, Greek, Vietnamese, Serbian and Thailand or (low comparison) Estonian. The readership rate is side by side with Czech (rank 15 with 2,4 million readers per month, and 90s very active users), followed by Indonesian (rank 16 with 2,3 million readers per month, and 50s very active users) and Finish (rank 17 with 2,2 million readers per month, and 90s very active users). Confirming it multiplication of potential reach once filled with contents.
  • Over 3,520 articles made during three project intervention in three different wikipedia: Indonesian, Javanese, and Sundanese. The number of article didn't include the articles made by Lontar project or writing class participants.

Wikimedia Cipta Jakarta edit

Three sub project created with the goal of identifying ways to reverse the editor trend:

Writing class edit

See June during writing (boiler) class result
  • Writing class performed best when the committee prepare incoming clueless participant with an encyclopedic style article for them to type in complete with its references to show them what an ideal wikipedia article suppose to look like.
  • However these "writing samples" run out very quickly.
  • The article sample (with encyclopedic writing style) already in Indonesian language is very difficult to obtain, never mind the copyright. Free license article sample is downright not available.
  • Based on this difficulties of obtaining free material for encyclopedia entry as "training material" using a valid reference in Indonesian language - there are heavy focused discussion of doing a REIR (Releasing Encyclopedia Indonesia (copy) Right) Project. The discussion cover in releasing existing encyclopedia in Indonesian language consisting approximately 17,000 encyclopedia articles written by Indonesian best scholars published in 1980. It is currently in a heavy and exclusive book format. However we are still unclear on how much it cost to do it legally.
  • The writing class also show an event with a fruitful result that saves volunteer energy and cost effective is best aimed to targeted audience from a university rather than random public.

Project class edit

One of the project class session
  • Project class performed best during budgeting class. The participants was excited and come out with their own plan on how to safe money for the project while trying it's best to maintain goal. Expectation meet reality.
  • Two netbooks are purchased to enable two participants of project class to participate in the program. The netbook at first was hold by Isabella Apriyana and Nico Marko, but then one change hands since Sundapedia 2011 Project Director requested the netbook in order to be mobile between Jakarta-Bandung and home-office activity to monitor Sundapedia 2011 progress. One laptop purchased for Wikimedia Cipta central administration since his suddenly broke and he was unable to work.

Coordination meeting edit

  • The coordination meeting performed best during recruitment of potential project director and organizers
  • The coordination meeting also beneficial in identifying potential organization to cooperate with
  • The coordination meeting performed worse during recruitment of professional & expert to help with projects. Only one out of several meetings are successful.
  • In total there are three universities explicitly expressing interest in training: Universitas Nasional Jakarta majoring in Economy (Jakarta), Universitas Sanata Dharma (Yogyakarta) majoring in English Literature focusing in Journalism, and IKIP Semarang (Semarang) majoring in Javanese Literature.

Beacon of Theology 2011 edit

  • Suffering the same faith as Indonesian language Wikipedia birthday party, in February 2011 an executive decision to sub-funded (more than half) Beacon of Theology 2011 project was taken following WMF decision in funding it less than half. The decision was taken using the assumption that WMF staff wasn't able to evaluate how much a micro project cost in Jakarta. The Project Director is upset and almost canceled the project in the absent of the funding. It is decided that capacity building grant will be used to funded project, cutting capacity building classes from 6 months to 3 months to cover the cost.
  • In return the committee was asked to do independent fundraising for the project. They came prepared with proposal and visited one church to another for additional funding and manage to raise approx. US$ 516,59. The lesson learned from this happening showed volunteer only able to fundraise 6.8 percent out of - a US$ 7.541,59 total budget needed to run a project. This is using the assumption that they have contacts and ability to do it. Making it impossible for micro project to run without grants. The committee end up printing project T-shirt and bought extra net book with the extra funding and make ends meet by donating their own money.

Papat Limpad edit

SEVEN MONTHS!
  • Papat Limpad also introduced as Javanese Language Wikipedia Revitalization Project would be the highlight of Wikimedia Cipta project. Not only that the project showed successful replication of Free Your Knowledge System (FYKs) writing competition in other language Wikipedia, it is also showed that a seven months project intervention are possible to be done!
  • Project Director and FYKs designer often receive questions of: "Are the participants returning after the competition?", unfortunately the answer is still "no". Some (very few, one or two) return, but a "no" answer would be sufficient considering how low the return rate is. However Papat Limpad proves that a seven months competition out of 12 months in a year is not a bad accomplishment considering the language is suffering lack of editors for years. It's just a realization that intervention program in order to make a sustainable impact need to be done repeatedly for five years until it finds it momentum to sustain itself in practice.
  • This projects proves that a true blue wikipedian although consider as "renewable resources", actually fall as very rare renewable resources who's contribution are often taked for granted. It is important for them to be appreciated for their contribution to society in delivering free knowledge into people hands possible.

Banjar Language Wikipedia Volunteer Identification Project edit

  • This is the first project involving inviting and funding volunteer come to Jakarta.
  • The session with Banjar Language Wikipedian pioneer serve lesson learn for both Wikimedia Indonesia and Arief. Previously Arief, through multiple channel, identified as wanting to reach us by criticizing, and wondering Wikimedia Indonesia part in supporting to other local language outside Java. After the fact laid out and resources to actually to run a project identified, we come to an understanding that running an offline project involving a third party is not easy. Whether there are a strong will presence from the volunteer, extra sacrifices will still need to be made in the form of funding or time.

Sundapedia 2011 edit

TBD. To date (December 1, 2011) manage to contribute a little over 500 articles and currently showing similar success as previous intervention.

Wikimedia-Lontar for Indonesian Writer edit

  • This project is the first cooperation Wikimedia Indonesia made with a Library, traditionally we only did outreach to Universities.
  • We learn that library need certain license compatibility between CC-Zero licenses and Open Data Commons Open Database License (ODbL). This is a homework for Wikimedia Indonesia's Creative Commons ID project.

Detail of expenditures edit

Please see details expenditures for Wikimedia Cipta main infrastructure. Other expenditures can be found through its own respective project can be find in the table below.

Amount in Indonesian Rupiah

Project Budget Actual Balance
105.733.329,- 101.012.588,- 4.720.741,-
41.500.000,- 41.500.000,-
17.600.000,- 14.379.978,- 3.220.022,-
14.400.000,- 13.576.568,- 823.432,-
89.598.000,- 85.937.742,- 3.660.258,-
21.028.950,- 21.028.950,- -
35.900.000,- 30.261.250,- 5.638.750,-
5.350.000,- 4.696.904,- 653.096,-
17.575.000,- 17.575.000,- -
Total 348.685.279,- 329.968.980,- 18.716.299,-

Amount underspent in US Dollars edit

Will you be requesting re-allocation of remaining grant funding? edit

Remaining grant funding returned on 27/12/2012

Financial Report edit

Please note that the budget breakdown will be in Indonesian Rupiah (Rp) for exact calculation, U.S. Dollar value (USD) only serve as a comparison purpose.

  • Estimate for total budget Rp 367.603.329 equal to US$ 40.844,81 exchange rate 1 USD ~ Rp. 9,000,-

Budget allocation phase 1 - Preparation and volunteer recruitment edit

Phase 1: Preparation and volunteer recruitment (duration: December 2010 to March 2011)
1 No Preparation and volunteer recruitment Qty Unit x Qty Unit x Unit Price (Rp) Total amount (Rp) Total amount (USD) Total expenditure Balance
A Communication (cellular) 2 persons x 13 months x 300.000,- 7.800.000,- 866,67 18.458.886,- (10.658.886,-)
B Administrative equipment (printing/paper/office supply) 4 months x 700.000,- 2.800.000,- 311,11 6.983.700,- (4.183.700,-)
C Meeting room rental x 18 sessions x 720.000,- 12.960.000,- 1.440,00 2.993.500,- 9.966.500,-
D Logistic (food and beverages) x 18 sessions x 500.000,- 9.000.000,- 1.000,00 17.770.744,- (8.770.744,-)
E Central coordination and administration (staff) 1 person x 13 months x 4.333.333,- 56.333.329,- 6.259,26 56,333,329,- 0
F Recruitment specialist/ Project consultant 1 person x 48 sessions x 900.000,- 43.200.000,- 4.800,00 12,229,243,- 30,970,757,-
G Local transportation x 18 sessions x 150.000,- 2.700.000,- 300,00 1,110,000,- 1,590,000,-
H Notebook x 15 units x 5.200.000,- 78.000.000,- 8.666,67 63,223,000,- 14,777,000,-
Subtotal 212.793.329 23.643,70 179.102.402,- (10.658.886,-)

Budget allocation phase 2 - Coaching edit

Coaching classes will start from January to June 2011 - see coaching schedule (changes periodically)
2 No Coaching Qty Unit x Qty Unit x Unit Price (Rp) Total amount (Rp) Total amount (USD) Total expenditure Balance
A Communication (cellular) 2 persons x - months x - - - 6.117.269,- (6.117.269,-)
B Administrative equipment (printing/paper/office supply) 4 months x 700.000,- 2.800.000,- 311,11 5.566.400,- (2.766.400,-)
C Meeting room rental x 24 sessions x 720.000,- 17.280.000,- 1.920,00 6.634.700,- 10.645.300,-
D Logistic (food and beverages) x 24 sessions x 500.000,- 12.000.000,- 1.333,33 8.996.989,- 3.003.011,-
E Central coordination and administration (staff) 1 person x - months x - - - 0 0
F Recruitment specialist/ Project consultant 1 person x 24 sessions x 900.000,- 21.600.000,- 2.400,00 20.739.243,- 860.757,-
G Local transportation x 24 sessions x 150.000,- 3.600.000,- 400,00 12.370.000,- (17.139.243,-)
Subtotal 57.280.000,- 6.364,44 60.424.601,- (11.513.844,-)

Budget allocation phase 3 - Implementation edit

Implementation classes will start from March to November 2011 - see implementation schedule (changes periodically)
3 No Implementation Qty Unit x Qty Unit x Unit Price (Rp) Total amount (Rp) Total amount (USD) Total expenditure Balance
A Communication (cellular) 2 persons x - months x - - - 0 0
B Administrative equipment (printing/paper/office supply) 3 months x 700.000,- 2.100.000,- 233,33 3.990.200,- 0
C Meeting room rental x 24 sessions x 720.000,- 17.280.000,- 1.920,00 0 0
D Logistic (food and beverages) x 24 sessions x 500.000,- 12.000.000,- 1.333,33 0 0
E Central coordination and administration (staff) 1 person x - months x - - - 0 0
F Recruitment specialist/ Project consultant 1 person x 24 sessions x 900.000,- 21.600.000,- 2.400,00 4.129.243,- 0
G Local transportation x 24 sessions x 150.000,- 3.600.000,- 400,00 8.750.000,- 0
Subtotal 56.580.000,- 6.286,67 16,869,443,- 56,580,000,-

Budget allocation phase 4 - Monitoring edit

Monitoring classes will start from March to November 2011- see monitoring schedule (changes periodically)
4 No Monitoring Qty Unit x Qty Unit x Unit Price (Rp) Total amount (Rp) Total amount (USD) Total expenditure Balance
A Communication (cellular) 2 persons x - months x - - - 8.036.297,- (8.036.297,-)
B Administrative equipment (printing/paper/office supply) 3 months x 700.000,- 2.100.000,- 233,33 12.784.165,- (10.684.165,-)
C Meeting room rental x 12 sessions x 720.000,- 8.640.000,- 960,00 3.050.812,- 5.589.188,-
D Logistic (food and beverages) x 12 sessions x 500.000,- 6.000.000,- 666,67 19.641.117,- (13.641.117,-)
E Central coordination and administration (staff) 1 person x - months x - - - 0 0
F Recruitment specialist/ Project consultant 1 person x 12 sessions x 900.000,- 10.800.000,- 1.200,00 27.696.793,- (16.896.793,-)
G Local transportation x 12 sessions x 150.000,- 1.800.000,- 200,00 15.103.550,- (13.303.550,-)
Subtotal 29.340.000,- 3.260,00 86.312.734,- (56.972.734,-)

Budget allocation phase 5 - Project evaluation & report edit

Evaluation phase starting from Mei 2011 to November 2011
Report will be done periodically once every three months in a year by consultant and final report will be done in December 2011.
5 No Project evaluation and report Qty Unit x Qty Unit x Unit Price (Rp) Total amount (Rp) Total amount (USD) Total expenditure Balance
A Communication (cellular) 2 persons x - months x - - - 0 -
B Administrative equipment (printing/paper/office supply) 3 months x 700.000,- 2.100.000,- 233,33 0 -
C Meeting room rental x 3 sessions x 720.000,- 2.160.000,- 240,00 0 -
D Logistic (food and beverages) x 3 sessions x 500.000,- 1.500.000,- 166,67 0 -
E Central coordination and administration (staff) 1 person x - months x - - - 0 -
F Recruitment specialist/ Project consultant 1 person x 6 sessions x 900.000,- 5.400.000,- 600,00 4.129.243,- -
G Local transportation x 3 sessions x 150.000,- 450.000,- 50,00 0 -
Subtotal 11.610.000,- 1.290,00 4.129.243,- 11.610.000,-

Total amount edit

Rp. 367.603.329 - US$ 40.844,81 (requested)
Rp. 367.059.991,90 - US$ 40.784,44 (received)
Rp. 346.838.423,- - US$ [~38.537,60] (spent)
Rp. 20.221.568,90 - US$ [~2,246.84] (balance)