Grants:Project/WikiProject X/CollaborationKit MVP/Timeline


Timeline for WikiProject X

edit
Timeline Date
Milestone 1: CollaborationKit correctly works with current MediaWiki January 2019
Milestone 2: WikiProject X pages on Wikipedia are fully updated to reflect current project status March 2019
Milestone 3: CollaborationKit forms represent theoretically adequate UX and workflows to justify testing April 2019
Milestone 4: CollaborationKit content handling meets theoretical threshold for production robustness May 2019
Milestone 5: Midpoint April-May 2019
Milestone 6: Schema- and i18n-related deployment blockers resolved June-August 2019
(partially completed)
Milestone 7: Deployment, or a deployment plan in play May-June 2019
(not completed)
Milestone 8: WikiProject adoption and testing of CollaborationKit yields some sort of results June-July 2019
(not completed)
Milestone 9: Iteration on CollaborationKit software to better meet user needs June-August 2019
(not completed)
Milestone 10: Final report September 2019


Monthly updates

edit

Please prepare a brief project update each month, in a format of your choice, to share progress and learnings with the community along the way. Submit the link below as you complete each update.

August 2018

edit

September - December 2018

edit

January - June 2019

edit

July - September 2019

edit

Is your final report due but you need more time?



Extension request

edit

New end date

edit

30 August 2019

Rationale

edit

Based on my conversation with Marti, I have decided to proceed with a 1-month sprint focusing exclusively on my CollaborationKit work, with support from Brian Wolff and Jack Phoenix, from the second week of April to mid May. I have updated the timeline and milestones above to reflect the new expectations, based on where we are currently with the project and the remaining work that needs to be done. This work should represent the bulk of the remaining development work, with the Midpoint report being submitted either during this sprint or after, and the following few months will be much lighter work primarily focused on deployment and addressing and assessing user feedback, including waiting periods for process to resolve, from which findings will be made for the final report.

Thus I am requesting a new end date of August, 2019. -— Isarra 19:25, 26 March 2019 (UTC)

Approved

edit

Approving a new end date of August 30, 2019. Marti (WMF) (talk) 23:48, 26 March 2019 (UTC)

Noting here that the new final report due date is 29 September 2019. -- Best, JTud (WMF), Grants Administrator (talk) 20:48, 28 March 2019 (UTC)

New midpoint date

edit

Explicitly requesting midpoint due date set at 15 May 2019, then, per above? -— Isarra 23:27, 29 March 2019 (UTC)

New midpoint date approved

edit

Approved: new midpoint report due date of May 15, 2019. Marti (WMF) (talk) 03:52, 30 March 2019 (UTC)