Grants:PEG/WM DE/Wikimedia Conference 2014/Report


Report accepted
This report for a Project and Event grant approved in FY 2013-14 has been reviewed and accepted by the Wikimedia Foundation.
  • You may still comment on this report on its discussion page, or visit the discussion page to read the discussion about this report.
  • You are welcome to Email grants at wikimedia dot org at any time if you have questions or concerns about this report.


Compliance and completion

edit
Did you comply with the requirements specified by WMF in the grant agreement?
Answer YES or NO.
Yes
Is your project completed?
Answer YES or NO.
Yes
Did you use any of the grant funds?
Answer YES or NO.
Yes

Activities and lessons learned

edit

This section describes what the grantee did, and what the grantee learned from implementing the project. This section should be useful to others implementing similar projects and is an opportunity for the grantee to reflect on the project's performance.

Activities

edit
Provide a detailed list of activities performed to complete this project, descriptions of these activities, and the amount of time spent on each activity. This section should also include a list of participants, or a link to pictures, blog posts, or videos from the project or event.

Please see the conference report here: https://meta.wikimedia.org/wiki/Wikimedia_Conference_2014/Feedback_evaluation

Expenses

edit
Please list all project expenses in a table here, with descriptions and dates. Review the instructions here.
These expenses should be listed in the same format as the budget table in your approved submission so that anyone reading this report may be able to easily compare budgeted vs. actual expenses.
Note that variances in the project budget over 10% per expense category must be approved in advance by Project and Event Grants program staff. For all other variances, please provide an explanation in the table below.

Please see the conference financial report here: https://meta.wikimedia.org/wiki/Wikimedia_Conference_2014/Budget_and_finances

Total project budget (from your approved grant submission)
TBD -- up to 117,600€ (~$162k)
Total amount requested from WMF (from your approved grant submission, this total will be the same as the total project budget if the Project and Event Grant is your only funding source)
up to 117,600€
Total amount spent on this project (this total should be the total calculated from the table above)
94.976,99 €
Total amount of Project and Event grant funds spent on this project (this total will be the same as the total amount spent if the Project and Event Grant is your only funding source)
94.976,99 €
Are there additional sources of revenue that funded any part of this project? List them here.
No.

Remaining funds

edit
Are there any grant funds remaining?
Answer YES or NO.
No
Please list the total amount (specify currency) remaining here. (This is the amount you did not use, or the amount you still have after completing your grant.)
n/a
If funds are remaining they must be returned to WMF, reallocated to mission-aligned activities, or applied to another approved grant.
Please state here if you intend to return unused funds to WMF, submit a request for reallocation, or submit a new grant request, and then follow the instructions on your approved grant submission.
n/a