editMilestone | 2020-2021 Round 1 | 2020-2021 Round 2 |
---|---|---|
WMF confirms eligibility | 15 October 2020 | 15 March 2021 |
Proposals due | 30 October 2020 | 1 May 2021 |
Decisions announced | 1 December 2020 | 1 June 2021 |
Grant term starts | 1 January 2021 | 1 July 2021 |
Progress report due | 30 July 2021 | 30 January 2022 |
Grant term ends | 31 December 2021 | 30 June 2022 |
Impact report due | 31 March 2022 | 28 September 2022 |
Audited financial report due | 30 April 2022 | 31 October 2022 |
This table explains important milestones for each round of the Annual Plan Grants (APG) process, from the submission date for letters of intent through the submission of audited financial statements at the conclusion of the reporting period. Each milestone links to process documentation about that event, while links to documents for each round may be found in the body of this table. For more information, you can review the proposal process documentation. See archived rounds.
NOTE: In 2018-2019, the process will follow a different timetable which will be shared with the organizations participating in the APG process. The process will not be accepting new FDC-APG organizations applicants before at least June 2019. Reporting requirements have not changed.
Milestone | 2015–2016 Round 2 | 2016–2017 Round 1 | 2016–2017 Round 2 | 2017–2018 Round 1 | 2018–2019 Round 1 |
---|---|---|---|---|---|
Letters of intent due | 1 novembre 2015 |
1 juillet 2016 |
1 novembre 2016 |
1 juillet 2017 |
Error: Invalid time. |
WMF assesses eligibility | 15 janvier 2016 Liste des pré-requis d’éligibilité |
15 juillet 2016 Liste des pré-requis d’éligibilité |
15 janvier 2017 Liste des pré-requis d’éligibilité |
15 juillet 2017 Liste des pré-requis d’éligibilité |
15 juillet 2018 Liste des pré-requis d’éligibilité |
WMF confirms eligibility | 15 mars 2016 | 15 septembre 2016 | 15 mars 2017 | 15 septembre 2017 | 15 octobre 2018 |
Proposals due | 1 avril 2016 |
1 octobre 2016 |
1 avril 2017 |
1 octobre 2017 |
1 novembre 2018 |
Community review until | 30 avril 2016 | 30 octobre 2016 | 30 avril 2017 | 30 octobre 2017 | {{{month}}} |
Staff assessments due | 8 mai 2016 Assessments |
8 novembre 2016 Assessments |
8 mai 2017 Assessments |
8 novembre 2017 Assessments |
{{{month}}} |
Deliberations | 13 May 2016 | 16 November 2016 | 1 May 2017 | 16 November 2017 | {{{month}}} |
FDC recommendation due | 1 juin 2016 Recommendation du FDC |
1 décembre 2016 Recommendation du FDC |
1 juin 2017 Recommendation du FDC |
1 décembre 2017 Recommendation du FDC |
{{{month}}} |
Board decision due | 1 juillet 2016 Décision du Board |
1 janvier 2017 Décision du Board |
1 juillet 2017 Décision du Board |
1 janvier 2018 Décision du Board |
1 janvier 2019 Décision du Board |
Appeals and complaints until | 8 juin 2016 | 8 décembre 2016 | 8 juin 2017 | 8 décembre 2017 | 8 décembre 2018 |
Progress reports Q2 due | 30 janvier 2017 |
30 juillet 2017 |
30 janvier 2018 |
30 juillet 2018 |
30 juillet 2018 |
Impact reports due | 28 septembre 2017 | 28 mars 2018 | 28 septembre 2018 | 28 mars 2019 | 28 mars 2020 |
Financial statements due [*] see notes | 28 octobre 2017 | 28 avril 2018 | 28 octobre 2018 | 28 avril 2019 | 28 avril 2020 |
[*] Notes
edit- Dates in this line are indicative. As per the grant agreements, audited financial statements are due 120 days after the end of an organization's fiscal year. This may vary depending on the organization. As of June 2017:
- Round 1: WMUK has a fiscal year ending on 31 January, so due date is 31 May
- Round 2:
- CIS has a fiscal year ending on 31 March, so due date is 31 July
- WMAM and WMNO have a fiscal year ending on 31 December, so due date is, as per round 1, 28 April